Default TimeSheet with time start and end during the day

The question is simple: is there a possibility to collect/introduce information about activities in timesheet with hour: minutes start and end. It's very import for Human Resources reports to store that kind of information like
Developer 1 : activity 1: 09:00 11:00 (2h)
Developer 1 : activity 2: 11:00 17:00 (6h)
br
  #2  
Old 2012-03-12
dhk dhk is offline
Senior Member
Site AdminSite Admin
 
Join Date: Apr 2006
Location: Corvallis, OR
Posts: 442
Default

Quote:
Originally Posted by mkokosz View Post
The question is simple: is there a possibility to collect/introduce information about activities in timesheet with hour: minutes start and end. It's very import for Human Resources reports to store that kind of information like
Developer 1 : activity 1: 09:00 11:00 (2h)
Developer 1 : activity 2: 11:00 17:00 (6h)
br
Project.net only collects the number of hours and the date those hours were worked, not which specific hours. This information, along with which project and which task, is included in the Time Submitted Report.
__________________
Dustin Kassman
Technical Support
Project.net
  #3  
Old 2012-03-15
mkokosz mkokosz is offline
Junior Member
Site AdminSite Admin
 
Join Date: Feb 2012
Posts: 2
Default

Hi, Thanks for Your answer:
I've found table in Oracle PN_TIMESHEET - are You going to collect this kind of data in future or it's for other purposes?
Best Regards
  #4  
Old 2012-03-16
dhk dhk is offline
Senior Member
Site AdminSite Admin
 
Join Date: Apr 2006
Location: Corvallis, OR
Posts: 442
Default

Personal working time calendars have actual start, lunch and end times in them but we only utilize those to compute the number of work hours for that resource in a day. At one time Project.net was designed to worry about times worked but none of our customers were ever interested in that capability; it was never implemented in the timesheet. We are actually working to remove anything related to this from the code and database in order to clean up and simplify both.
__________________
Dustin Kassman
Technical Support
Project.net
 

Tags
task to user, time, timesheet

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off

Forum Jump


All times are GMT -4. The time now is 09:02 PM.


Powered by vBulletin® Version 3.8.1
Copyright ©2000 - 2014, Jelsoft Enterprises Ltd.
© 2005-2008 Project.net